The Master Plan is based on the following sections:

            1- Industrial Area

            2- Services & Logistics Area

            3- Commercial Area

            4- Residential Area


Phasing Description
The establishment of the Industrial Park shall be performed in four main phases as follows:

Phases

Area x 1000m2

Contents

Phase I

610

1.       Site Terracing for Phase I

2.       Roads for Phase I

3.       50% of Building B

4.       Gas Station

5.       Phase I areas respective Main MV 

          distributor station with its MV cables loops.

6.       Phase I areas respective transformer

          substations

7.       The Booster pump station

8.       20% of the domestic water, fire fighting,

          irrigation & drainage pipe network

9.       20% of the Telecommunication network

10.     20% of the Natural Gas distribution network

Phase II

540

1.       Site Terracing for Phase II

2.       Roads for Phase II

3.       15% of the SFB and Warehouses

4.       Phase II areas respective Main MV 

          distributor station with its MV cables loops

5.       Phase II areas respective transformer

          substations

6.       The water treatment station

7.       25% of the domestic water, fire fighting,

          irrigation & drainage pipe network

8.       25% of the Telecommunication network

9.       25% of the Natural Gas distribution network

10.     Housing will start

Phase III

340

1.       Site Terracing for Phase III

2.       Roads for Phase III

3.       Building B finishes

4.       40% of the SFB and Warehouses

5.       Phase III areas respective Main MV

         distributor station with its MV cables loops

6.       Phase III areas respective transformer

          substations

7.       30% of the domestic water, fire fighting,

          irrigation & drainage pipe network

8.       30% of the Telecommunication network

9.       30% of the Natural Gas distribution network 

Phase IV

510

1.       Site Terracing for Phase IV

2.       Roads for Phase IV

3.       45% of the SFB and Warehouses

4.       Phase IV areas respective Main MV

          distributor station with its MV cables loops

5.       Phase IV areas respective transformer

          substations

6.        The Booster pump station

7.       25% of the domestic water, fire fighting,

          irrigation & drainage pipe network

8.       25% of the Telecommunication network

9.       25% of the Natural Gas distribution network

 

 

HOME PAGE | FOUNDERS | NEWS | PROJECT IN  FIGURES | MASTER PLAN | INFRASTRUCTURE

PRESS | FACILITIES | APPLICATION FORM | EGYPT ECONOMY | PHOTO GALLERY

 | EGYPT MAP | 6th OCTOBER MAP | PIIP ON GOOGLE | CONTACT US

 

Polaris Parks Copyright © 2008